Narrabri North Environmental Management

 

Stage 2 Project Approval

Project Approval (PA) 08_0144 MOD 2

 

Stage 1 Project Approval

(currently being surrendered)

Project Approval (PA) 05_0102

 

Stage 2 Environmental Assessment

Environmental Assessment

Contents and Executive Summary

Section 1 - Introduction

Section 2 - Description of the Longwall Project

Section 3 - Issue Identification and Prioritisation

Section 4A - Enviromental Features, Management Measures & Impacts

Section 4B-1 - Environmental Features, Management Measures & Impacts

Section 4B-2 - Environmental Features, Management Measures & Impacts

Section 5 - Draft Statement of Commitments

Section 6 - Evaluation/Justification of the Project

Section 7 - References

Section 8 - Glossary

Appendices 1 - 4

 

Specialist Consultant Studies Compendium

Volume 1 - Cover Page and Index

Part 1 - Subsidence Assessment - A

Part 1 - Subsidence Assessment - B

Part 1 - Subsidence Assessment - C

Part 1 - Subsidence Assessment - D

Part 1 - Subsidence Assessment - E

Part 1 - Subsidence Assessment - F

Part 2 - Groundwater Assessment - A

Part 2 - Groundwater Assessment - B

Part 2 - Groundwater Assessment - C

Part 2 - Groundwater Assessment - D

Part 2 - Groundwater Assessment - E

Part 3 - Surface Water Assessment

Part 4 - Ecological Assessment

Volume 2 - Cover Page and Index

Part 5 - Aboriginal Heritage Assessment - A

Part 5 - Aboriginal Heritage Assessment - B

Part 5 - Aboriginal Heritage Assessment - C

Part 5 - Aboriginal Heritage Assessment - D

Part 6 - Noise and Vibration Assessment - A

Part 6 - Noise and Vibration Assessment - B

Part 6 - Noise and Vibration Assessment - C

Part 7 - Air Quality Assessment

Part 8 - Greenhouse Gas Assessment

Part 9a - Soils Assessment (Mine Site)

Part 9b - Soils Assessment (REA, Brine Ponds and Pipeline)

Part 10 - Non-Indigenous Heritage Assessment

 

Stage 2 EPBC Assessment

EPBC Assessment

EPBC Approval

 

Mining Lease

ML 1609

 

Mining Operations Plan (MOP)

Mining Operations Plan

Plans

 

Environment Protection Licence

EPL 12789

 

Stage 2 Environmental Management Plans

Aboriginal Cultural Heritage Management Plan

Air Quality Monitoring Program

Energy Savings Action Plan

Environmental Management Strategy

Landscape Management Plan

     Rehabilitation Management Plan

     Mine Closure Plan

Noise Management Plan

Waste Management Plan

 

Stage 1 Environmental Management Plans

Site Water Management Plan (to be replaced with Stage 2 plan)

 

2011 Independent Environmental Audit

Audit Report

Action Plan

 

Current Annual Environmental Management Report (AEMR)

AEMR 2010 - 2011

Plan 3 - Land Preparation

Plan 4 - Mining and Rehabilitation

Appendix 1 - PA 05_0102 MOD 1 & PA 08_0144

Appendix 2 - EPL 12789

Appendix 3 - Compliance Reviews

Appendix 4 - Dust Monitoring Results

Appendix 5 - Surface Water and Wet Weather Discharge Results

Appendix 6 - Groundwater Monitoring Data

Appendix 7 - Noise Monitoring Results

Appendix 8 - Meteorological Data

 

2009-2010 Annual Environmental Management Report (AEMR)

AEMR 2009 - 2010

Plan 3 - Land Preparation

Plan 4 - Mining and Rehabilitation

Appendix 1 - PA 05_0102 MOD 1

Appendix 2 - EPL 12789

Appendix 3 - Compliance Reviews

Appendix 4 - Dust Monitoring Results

Appendix 5 - Surface Water and Wet Weather Discharge Results

Appendix 6 - Groundwater Monitoring Data

Appendix 7 - Noise Monitoring Results

Appendix 8 - Meteorological Data

 

2008-2009 Annual Environmental Management Report (AEMR)

AEMR 2008 - 2009

Plan 3 - Land Preparation

Plan 4 - Mining and Rehabilitation

Appendix 1 - PA 05_0102

Appendix 2 - EPL 12789

Appendix 3 - Compliance Reviews

Appendix 4 - Dust Monitoring

Appendix 5 - Groundwater Monitoring Data

Appendix 6 - Blast Monitoring

Appendix 7 - Routine Operational Noise Monitoring

Appendix 8 - Meteorological Data

Appendix 9 - Quarterly Surface Water Monitoring

 

Community Consultative Committee (CCC)

Environment Monitoring Report

14 May 2008

13 August 2008

19 November 2008

25 February 2009

27 May 2009

26 August 2009

8 December 2009

2 March 2010

1 June 2010

7 September 2010

14 December 2010

5 April 2011

7 June 2011

26 July 2011

8 November 2011

 

Meeting Minutes

14 May 2008

13 August 2008

19 November 2008

25 February 2009

27 May 2009

26 August 2009

8 December 2009

2 March 2010

1 June 2010

7 September 2010

14 December 2010

5 April 2011

7 June 2011

26 July 2011

8 November 2011

 

Next Meeting

9 February 2012

 

Complaints Register

2008 Complaints (8 complaints)

2009 Complaints (8 complaints)

2010 Complaints (2 complaints)

2011 Complaints (5 complaints)

2012 Complaints (no complaints to date)